A360 works underway – phase three
Works on the A360 to install high-voltage cabling under the road continue to progress well. Work will continue over the bank holiday weekend and we will then begin the final phase of trenching works between Druids Lodge and the Longbarrow roundabout.
The project is on schedule to be completed by mid-July.
Work is being carried out seven days a week and includes some overnight working so the project can be completed as quickly and safely as possible.
Traffic is being diverted via the A345 and sections of the A303 and A360.
The road between Stoford and Woodford remains open with temporary traffic lights used to manage traffic flow as needed.
Please do continue to plan your journeys and allow extra time if you’re travelling at peak times.
We are working with people who live and work along the A360 to safely manage their access throughout the works. If you have any questions about access to homes and businesses on the A360, please call 03301 755 675 or email info@a360temporaryclosure.co.uk
Wiltshire Council improvement works on the A360
Over the coming weeks, Wiltshire Council will also carry out additional improvement works on the A360 while the closure is in place. This will include pothole and road edge repairs, and drainage improvements.
Diverted traffic
We have been conducting traffic monitoring to record the volume, weight and speed of traffic on the diversion route and local road network. Wiltshire Police has also conducted speed and weight checks in the area.
Wiltshire Police will continue to carry out speed and weight checks on the surrounding roads and we will continue to take a coordinated approach to traffic monitoring with National Highways and Wiltshire Council.
If you see a driving offence, such as dangerous, careless or inconsiderate driving, you can report it through Wiltshire Police’s website.
Wiltshire Police review every report it receives and uses the information to build its intelligence picture, inform policy and consider what action may be taken.
Frequently asked questions
You can find frequently asked questions about the closure and the diversion on the project website.
Contact us
You can contact us by phone or email:
Email: info@a360temporaryclosure.co.uk
Tel: 03301 755 675 (08.30 - 17.30 Monday - Friday, excluding bank holidays).
If you leave a message, we will return your call.
Website: a360temporaryclosure.co.uk